SAGARMALA COASTAL BERTH SCHEME

  • Construction of Coastal Berth of 250 mtr at Karwar Port :  Rs.61  Cr. 

Obtained Environmental clearance. Tender is floated and last date for tender submission was 30.08.2019.

  • Construction of Existing south breakwater by 145 m& construction of new north breakwater of 1160 m at Karwar Port : Rs.215.00 Cr.

Govt has accorded Administrative Approval for the Total amount of Rs. 215.00 Cr which includes the Construction of  880 mtr Northern Breakwater of estimated cost of Rs. 125.00 Cr. and Extension of Southern Breakwater to the extent of 145 mtr and Construction of (1160-880) 280 mtr Northern Breakwater of estimated cost of Rs. 90.00 Cr. The Construction of Northern Breakwater from CH. 880m to 1160m i.e, 280m is to be carried out after construction of 880m Breakwater in First phase at the cost of Rs. 51.00 Cr. and Extension of Southern Breakwater of length 145 mtrs amounting Rs. 39.00 Cr. is to be taken up.

  • Capital dredging at Old Mangalore Port (Bengre side) : Rs.29.00 Cr.

Accorded the Administrative approval and submitted to the technical sanction. Obtaining the Rapid EIA Study & CRZ clearance is under progress. Action will be taken for conducting Public hearing with prior notifications.  

  • Construction of Coastal berth at Old Mangalore Port : Rs.65.00 Cr.

Accorded the Administrative approval and submitted to the technical sanction. Obtaining the Rapid EIA Study & CRZ clearance is under progress. Action will be taken for conducting Public hearing with prior notifications.